Presa eléctrica Karuma: el Comité Directivo inspecciona los trabajos con progreso al 94%

Fecha: 25/06/2019

 

Fuente: Softpower 

 

The Project Steering Committee led by Eng Dr Badru M. Kiggundu has concluded its two-day inspection of the Karuma Interconnection Line and 600MW Karuma Hydropower project.

Overall progress in the construction works for the hydro power dam is now at 94 percent down from 79 percent as at August 2018 when President Yoweri Museveni inspected the works.

The 94 percent completion rate follows the successful 3rd stage river Diversion, installation of generation components for Units 1 to 5 and civil works across the project in the final stages.

The project steering committee was led on a site inspection by Eng. Timothy Mubbala, the Assistant Project Manager to the ongoing works at the Right Embarkment Dam, switch yard, underground Power House and Transformer Cavern.

After the visit, the PSC team will make a comprehensive report to President Museveni on the project progress, achievements, challenges faced and way forward as the project nears completion.

In August last year, President Museveni inspected the project. He toured the site including the dam and intake, to the underground Power House, Surge Chamber and the underground Tailrace Tunnel.

Commissioned in August 2013, the project is scheduled to be complete in December this year. The 600MW capacity dam is located on the Nile River, 110km downstream of Lake Kyoga.

It is being constructed by Sinohydro, a Chinese state-owned hydropower engineering and construction company.

In addition to the anticipated capacity of 600 MW, the project has had a major skills transfer, especially among the youth, according to the government of Uganda.

According to Sinohydro, more than 6,000 Ugandan youths have been employed at the construction site over the course of civil works, and most of them have been able to acquire a wide range of multiple skills (in structural design, metal welding and rock blasting among others) from expert engineers.

Government says the completion of the project will significantly boost Uganda’s electricity supply and facilitate the much needed industrialization.

Uganda’s current electricity generation stands at 1,167MW following the recent commissioning of Isimba power dam. This capacity will be increased to 1,767MW once Karuma is completed.

 

 

Otras Noticias
Acuerdo de Asociación Económica UE - Kenia

Nuevo hito para la Presidencia española con el Acuerdo de Asociación Económica UE - Kenia...

Global Gateway: La Comisión Europea y el Grupo del Banco Africano de Desarrollo desbloquean nuevos fondos para proyectos de infraestructuras en África

Global Gateway: La UE y el BAfD, nuevos fondos para proyectos de infraestructura en África...

El Camerún acoge una misión de asistencia técnica del FMI de dos semanas de duración

  Fuente: Business Cameroon   Currently, a technical assistance mission of the IMF is visiting Cameroon. Led by Jean Luc Helis, the mission will assess, for t...

Resumen del Plan de transición energética de Uganda

El informe de 108 páginas prevé un auge de la construcción en Uganda....