Industries, roads, offices are all mushrooming from different corners of Kampala city. These developments create growing demand for electricity in Kampala Metropolitan Area which contributes about 70 per cent of Uganda’s national demand currently at about 653 megawatts at peak. This demand is expected to grow to 987MW by 2030.

However, there is need for the transmission infrastructure used to sell power to electricity distributor, Umeme to meet the augmenting demand.
Government last year signed a $125m (Shs461b) loan from Japan International Cooperation Agency (JICA) to implement the Kampala Metropolitan transmission system improvement project.

Government through the Uganda Electricity Transmission Company Limited will construct new 220 kilovolt substations to upgrade from the present 132kV.
According to UETCL, there is urgent need to avoid severe capacity deficit in Kampala.

“Currently, the installed primary substation capacity of Kampala metropolitan area is 460MVA, hence the need to urgently reinforce the metropolitan transmission grid in order to avoid a severe capacity deficit,” Ms Pamela Byoruganda, principal public relations manager UETCL, says.

She also emphasised that the project aims to strengthen reliability and security of power supply.
For this to be realised, UETCL will increase the primary substation capacity of the area by an additional 890MVA and enhance the capacity of transmission lines in the area.

The transmission company will, for instance, upgrade Mutundwe substation, renovate and improve the capacity of Kawaala substation. 

 

 

Otras Noticias
Los consumidores tienen motivos para sonreír ante la presa Isimba

Fuente: The Observer   The installed capacity of Uganda’s electricity generation increased to 1,177MW in March 2019, following the commissioning of the Isi...

La mayor generación eléctrica de Uganda

Fuente: The Independent   The installed capacity of Uganda’s electricity generation increased to 1,177 MW in March 2019, following the commissioning of the...

El BAfD lanza una convocatoria de propuestas para la adaptación al cambio climático

La dotación de la primera Ventana de Acción por el Clima es de 258 millones de dólares....

El Banco Mundial está satisfecho con los logros del Fondo Innov Invest

El Banco Mundial, en colaboración con el Ministerio de Hacienda, acaba de elaborar un nuevo informe de situación sobre el Fondo Innov Invest (FII). Al términ...