The board of the African Development Bank (AfDB) has approved the Transmission Company of Nigeria’s, TCN’s, NTEP -1 projects in a board resolution in Abidjan.

The NTEP is one of the projects under TREP financed by AfDB that is targeted at rehabilitating and expanding parts of the transmission grid in the North West, South South and the South East.

The project would reconstruct old transmission lines and build new ones as well as construct new substations, contributing to further increase in TCN’s transmission capacity.

In a statement made available to Vanguard by the General Manager (Public Affairs), Ndidi Mbah, it stated that, even though the approval has just been given, the company had already concluded environmental studies including resettlement action plan in which people that would be affected by the acquisition of the Right of Way (RoW) for the proposed transmission lines were identified, the report had been submitted to AfDB.

“The advert for the pre-qualification of contractors had been carried out under advance procurement and evaluation of submissions from consultants that submitted “Expression of interest” for the procurement of consultancy for the project is on-going.

“Adopting the use of advance procurement in the execution of its projects, which has given TCN lead time, reducing procurement period by 6months.

“The procurement processes for the project is about 70 percent completed, meaning that execution of the projects under NTEP-1 would soon commence in earnest, even though it has just been approved by the AfDB board.

TCN further noted that the NTEP-1 projects would address some transmission lines and substations requirements in the North West, South South and South East regions of the nation.

“In the North West, the projects that would be executed include the construction of 212KM Double Circuit 330kV Quad conductor (Kaduna to Kano); installation of 2x150MVA and 2x60MVA transformers and bay extensions in Zara.

“Installation of 2x150MVA and 2x60MVA transformers with associated bay feeders and bay extensions in Kaduna Millennium city; installation of 2x60MVA transformers and outgoing feeders in Rigasa Kaduna; and the installation of 2x60MVA transformers and out-going feeders in jaji, Kaduna.

“The substations would all have turned in and turn out transmission lines.

In the South South and Sourh East, NTEP-1 would reconstruct the 107KM double circuit Delta-Benin transmission lines into a 330kV quad line; reconstruct the 138KM Alaoji- Ihiala – Onitsha Single Circuit line into 330kV Double Circuit Quad line. “

TCN also noted that NTEP-2 which would execute projects mainly in the North East and parts of the central states of the nation is also in the pipeline and has reached advanced stage on the funding processing.

Otras Noticias
El Foro Económico Mundial elige la industria automovilística marroquí como modelo

Fuente: Infomédiaire L’expérience de l’industrie automobile marocaine présente de “précieuses” leçons pour les d’autres pays africains, a soulign...

El mercado competitivo es el catalizador de la industrialización del Camerún

  Fuente: Journal du Cameroun   The government of Cameroon should strive to encourage a competitive business environment in order to attract more investors, e...

Uganda encabeza la lista de países africanos con marcos reglamentarios de electricidad bien desarrollados

  Fuente: Alternative Energy Africa   Uganda has for the third time in a row emerged as the top performer in this year’s Electricity Regulatory Index Report...

El consumo de energía en África tiene un enorme potencial de crecimiento, dice la EIA

  Fuente: Punch   Electricity consumption in Africa, on both a total and a per-person basis, is relatively low, but has tremendous growth potential, the Unite...